  • West Side Abutment Concrete Pour and East Side Cofferdam Installation This Week
    Notices, Project Status
    Valley Road Bridge Project Starting April 2018
    Notices, Project Status

    The Contractor is Brunalli Construction of Southington, CT. Utility work will occur in early April and is required to set up the bridge for demolition and reconstruction. The Valley Road Bridge is expected to be closed until December 2018 with final completion of the project in late Spring 2019. Fairfield Engineering and Public Works will provide updates to the neighborhood after meeting with Contractor in late March.

    Public Information held on 11.12.13
    Notices, Project Status

    Public Information held on 11.12.13. The Town has selected the Steel Beam Bridge alternative to replace the existing bridge. Next steps include scope development for final design, fee negotiations and contract preparation to move into the Final Design Phase.

    Public Information Meeting to be held on 11.12.13
    Notices, Project Status

    Public Information Meeting to be held on 11.12.13 at the Stratfield Elementary School, 1407 Melville Avenue, Fairfield

    Preliminary Engineering Report submitted
    Notices, Project Status

    Preliminary Engineering Report submitted to Town & ConnDOT’s Consultant Liaison Engineer

    Structure Type Study Report submitted
    Notices, Project Status

    Structure Type Study Report submitted to Town & ConnDOT’s Consultant Liaison Engineer.

    Preliminary Geotechnical Engineering Memorandum submitted
    Notices, Project Status

    Preliminary Geotechnical Engineering Memorandum submitted to Town & ConnDOT’s Consultant Liaison Engineer

    Preliminary Hydraulics Report submitted
    Notices, Project Status

    Preliminary Hydraulics Report submitted to ConnDOT’s Consultant Liaison Engineer for review.

    Drilling operations to commence
    Notices, Project Status

    Drilling operations for subsurface investigations to begin the week of September 30, 2013.

    Field survey & wetlands delineation completed
    Notices, Project Status

    Field survey & wetlands delineation completed in March 2013. The next step is complete Hydraulics Analysis followed by Subsurface Investigations and Structure Type Study